Decision on Connections Reform Package (TM04+)
- Content:
- Decision
- Dyddiad cyhoeddi:
- Sector diwydiant:
- Distribution Network,
- Transmission Network
We are publishing a suite of decision and supporting documents to enable connections reform, collectively known as the TM04+ reform package.
The principal overarching document (main link below) provides an overview of the whole TM04+ reform package, including a summary of responses to our February 14 minded-to consultation.
In the subsidiary documents you will find:
- decisions on Code Modifications (CM095, CMP434, CMP435)
- decisions on Connections Methodologies (Gate 2 Criteria Methodology, Project Designation Methodology, Connections Network Design Methodology).
- decision on the Licence Changes (in response to our February 14 statutory consultation) including Licensee Notice and Appendices' A-C with tracked changes.
- Impact Assessment
The Impact Assessment, which underpins our decisions, sets out an appraisal of the potential impacts of these reforms across a spectrum of areas, such as consumers, network build, economic growth and outlines benchmarks of success.
Altogether, the TMO4+ reform package enables a new electricity connections process that embeds ‘ready’ and ‘needed’ criteria into decision-making when managing requests for electricity connections.