- Publication date
- 16th April 2020
- Information types
- Guidance
- Policy areas
- Corporate information
- Electricity - distribution
- Electricity - offshore transmission
- Electricity - retail markets
- Electricity - transmission
- Electricity - wholesale markets
- Enforcement
- Environmental programmes
- ECO
- Domestic RHI
- Non-Domestic RHI
- FIT
- REGO
- RO
- CCL
- WHD
- GER
- SEG
- Gas - distribution
- Gas - retail markets
- Gas - transmission
- Gas - wholesale markets
- Licences, codes and standards
This page has been replaced by a newer version. Go to our June 2020 priorities update
Our immediate priorities
We are prioritising work on our response to the crisis. We are working closely and collaboratively with government, the energy industry, consumer organisations and other stakeholders to ensure that we can meet this overarching objective.
We will also deliver our statutory obligations and progress time-critical work, being mindful of stakeholder capacity to engage.
We will continue to update this page with information for licensees, and will assess and adapt our approach as the situation develops.
Statutory obligations and time-critical activities
Until 30 June, we will prioritise work in the areas listed below. We will reassess these regularly and will update activities where needed.
Area | Activities |
---|---|
Retail energy markets |
|
Wholesale energy markets |
|
Energy systems & networks |
|
Government environmental & social programmes |
|
Cross-cutting |
|
Stakeholder engagement we will continue
Over the coming weeks, we will continue to engage stakeholders to understand how we can best progress work on the activities outlined below.
Area | Activities |
---|---|
Retail energy markets |
|
Energy systems & networks |
|
Stakeholder engagement we are delaying or postponing
We are delaying or postponing a range of activities that we consider less time-critical in the short-term to consumer protection and security of supply. This is to enable stakeholders and Ofgem to prioritise response to the coronavirus (COVID-19) crisis, and focus time and resource to supporting customers and the market during this difficult period.
Where possible, and only where we are confident that it won’t impede our own response to the crisis, we may continue to pursue internal work, including to implement our decarbonisation action plan. This will enable us to make progress as quickly as possible once the immediate crisis has passed, and when industry and other stakeholders have sufficient capacity to engage.
The following table sets out a number of planned projects where publication was due in Spring 2020 but where we have now decided to postpone publication to the dates shown in the table. We will regularly review these plans.
Area | Activity | Revised publication date |
---|---|---|
Retail energy markets |
|
30 April 2020 |
|
TBC June 2020 | |
|
TBC June 2020 | |
|
TBC June 2020 or later | |
|
TBC June 2020 or later | |
|
TBC june 2020 or later | |
Wholesale energy markets |
|
TBC June 2020 or later |
|
TBC June 2020 or later | |
Energy systems & networks |
|
TBC June 2020 or later |
|
TBC June 2020 or later | |
|
TBC June 2020 or later |
|
Licensing, codes & standards |
|
TBC June 2020 or later |
Regulatory implications by sector
The following is a non-exhaustive summary of key regulatory implications, including relating to some industry programmes.
We expect licensees to prioritise customer and staff safety and will be pragmatic in our approach to compliance during this period. Licensees should not be afraid to do the right thing for their customers.
Jump to:
- Retail energy markets
- Wholesale energy markets
- Energy systems & networks
- Government environmental & social programmes
- Cross-cutting activities
Retail energy markets
Supplier obligations
Our overarching objectives in working with suppliers throughout the coronavirus (COVID-19) national crisis are to:
- ensure that consumer needs are met, particularly the needs of people in vulnerable situations.
- maintain secure, reliable and safe supplies of energy to GB consumers.
- ensure the safety and protection of consumers and industry workforce.
On 8 April we published a framework on regulatory flexibility. It outlines our expectations on suppliers for what is high priority now and must be delivered, and what can be deprioritised if necessary. The framework explains our pragmatic approach to compliance activity related to core, ongoing customer-facing aspects of supplier activity.
Assuming there is no change in circumstances, this framework will remain in place until 30 June 2020. We will review the case for extending and/or amending it, based on circumstances at the time of review.
Supplier regulatory reporting
We expect suppliers to continue their regulatory reporting, to ensure we have a clear picture of the market during this period.
We have asked suppliers to respond to a new mandatory information request to help us manage the crisis.
Recognising the circumstances, we have extended supplier reporting on a number of requests for information. The following will now be due in July 2020, although we expect this to include all data since the last reporting period:
- social obligations reporting
- complaints data reporting
- guaranteed standards of performance reporting.
Smart meter programme
Suppliers are obligated by Government to ‘take all reasonable steps’ to deliver the smart meter rollout by the end of 2020.
Within that, we have advised suppliers to:
- follow government guidance on coronavirus (COVID-19)
- adopt appropriate measures to protect their customers and staff.
We have issued guidance outlining the minimum steps that suppliers should be taking to minimise risk of exposure during installations, and confirmed that suppliers may temporarily deprioritise non-essential installations. Suppliers are expected to focus particularly on the wellbeing of their vulnerable customers and on customers at risk of going off supply.
In response to the implementation of the most recent social distancing measures:
- Energy UK has announced that its members will halt ‘all non-essential field activities’
- Major suppliers have indicated that only emergency installations will go ahead.
We expect suppliers to keep this reduction in activity under active review, taking into account the latest government guidance on coronavirus (COVID-19).
Switching programme
On 31 March, the Switching Delivery Group decided to delay entry to to User Entry Process Testing (UEPT). UEPT is the first testing stage that suppliers must complete within six months. The decision means suppliers can suspend testing preparation during the national crisis.
The programme is working on a revised delivery plan. We will agree the revised plan through usual programme governance so that any preparation activites that programme stakeholders can deliver is completed in the most cost-effective way.
The programme and its representatives will ensure all programme stakeholders are kept up to date.
Wholesale energy markets
Energy generator obligations
The wholesale energy market is playing a key role in delivering secure supplies of energy for consumers during this difficult time.
Market participants should raise any issues that cause security of supply concerns with the Department for Business, Energy & Industrial Strategy, the System Operators and Ofgem. To contact Ofgem on these issues, email: COVID19@ofgem.gov.uk.
As usual, we expect gas and electricity market participants to alert us to any risks of significant compliance failures or actual non-compliance, if and when they arise, at the first opportunity.
Participants should be able to set out why they feel you are unable to comply and what alternative or contingency steps they have taken to deliver your obligations to the best of their ability.
We will consider any such circumstance in its context, including any official Government advice and logistical challenges outside of their control (such as staffing availability and supply chain dependencies).
REMIT compliance
REMIT is an EU regulation on energy market integrity and transparency (No 1227/2011).
We take any breach of REMIT prohibitions and obligations extremely seriously. We would view any attempt to take advantage of a national emergency as a serious aggravating factor.
Following Government advice on coronavirus (COVID-19) measures, we understand that many market participants will have implemented working from home arrangements. REMIT continues to apply regardless of working arrangements.
In the case where working from home arrangements impose technical limitations on trading supervision and the broader control environment, we expect market participants to consider what steps they could take to mitigate outstanding risks. This could include, for example:
- enhanced monitoring, or
- retrospective review once the situation has been resolved.
If market participants have concerns about REMIT compliance during this time they should contact us at REMIT@ofgem.gov.uk
Where any issues are due to the coronavirus (COVID-19) situation, we will take this fully into account.
We continue to review the situation, and monitor for market abuse. We will take action where necessary.
Energy systems & networks
Network company obligations (transmission and distribution)
Our overarching objectives in working with network companies throughout the coronavirus (COVID-19) national crisis are to:
- ensure that consumer needs are met, particularly the needs of people in vulnerable situations.
- maintain secure, reliable and safe supplies of energy to GB consumers in the short to medium-term (i.e. through to the end of next winter).
- ensure the safety and protection of consumers and industry workforce.
On 8 April, we published a framework on regulatory flexibility. It outlines our expectations on network companies for what is high priority now and must be delivered, and what can be deprioritised if necessary. The framework explains our pragmatic approach to compliance activity related to core, ongoing customer-facing aspects of network activity.
We will continue to ensure our approach to the wider regulatory programme for the energy networks, including the ongoing monitoring and delivery of the existing RIIO-1 network price controls, remains consistent with these overarching objectives.
Assuming there is no change in circumstances, this framework will remain in place until 30 June 2020. As we approach that time, we will review the case for extending and/or amending it, based on circumstances at the time of review.
System operator obligations
We expect system operators:
- to be ensuring the secure and reliable operation of the electricity and gas systems as their first priority, and
- to continue to deliver their critical core functions in line with their licence, and
- in the case of the Electricity System Operator, deliver its Forward Plan.
Given the new challenges posed by the coronavirus (COVID-19), we want to have early sight on potential risks to the system and any impact on the system operators’ ability to effectively deliver any obligations or deliverables.
We will then work with the system operators to provide clarity on our views, recognising the enabling framework provided to network companies on 8 April.
RIIO-1 network price controls
We are discussing with stakeholders ways to reduce the regulatory burden from operating a range of RIIO-1 network price control processes this year, including the annual reporting requirements.
View a summary of amendments to the RIIO-1 programme for 2020.
RIIO-2 network price controls
For RIIO-2, our plan remains to publish final determinations by the end of 2020, and for the new controls to begin from 1 April 2021.
We propose to continue working towards publishing a consultation on our draft determinations for the transmission and gas distribution sectors and Electricity System Operator (ESO) controls in early July 2020, followed by a consultation on the electricity distribution sector methodology (RIIO-ED2) in late July 2020.
Given social distancing guidelines, we are not holding public open hearings ahead of the RIIO-2 draft determinations. We will continue to hold bilateral and working group meetings as normal, using teleconference or video conference facilities.
We welcome contact from stakeholders if they want to discuss any issues raised in the Challenge Group reports, Independent Customer Engagement Groups/User Group report or in the wider call for evidence responses published in January and February this year.
We will keep the RIIO-2 programme under regular review, and put in place a contingency plan should a worsening of impacts from the national crisis make it unfeasible to deliver the existing RIIO-2 programme by 1 April 2021.
Government environmental & social programmes
Information on delivery of Government environmental and social programmes
Where licensees are obligated under the government schemes we deliver, we expect that they will look to meet their obligations. This includes ensuring that they will be able to meet any Feed-in Tariff and Renewables Obligation payments.
We continue to deliver our statutory functions in administering Government environmental and social programmes. We are prioritising areas which have the most impact on participants, such as scheme payments and enquiries, but are unable to pause work or adjust deadlines laid out in the Regulations.
We are working with Government to look at if any changes are appropriate, and can be made.
All work carried out under the programmes:
- must follow the latest Government guidelines on going to work and social distancing, including sector-specific guidance.
- should be reviewed by suppliers working with their supply chain to understand if it is possible for the activity to continue whilst meeting the requirements of Government advice.
- Energy Company Obligation (ECO) work should only be carried out where it is considered 'essential repairs and maintenance' by the tradespeople carrying out the work before it is undertaken, with all activities in line with the latest Government advice, and with access to the property confirmed by the homeowner in advance.
We expect monitoring to continue as part of any installation work, where it does not conflict with the latest Government advice. This is to avoid poor-quality installations which could lead to further issues requiring home visits.
Suppliers concerned that they will not be able to meet monitoring requirements on time, should contact us at eco@ofgem.gov.uk as soon as they can to discuss alternatives.
Cross-cutting activities
Market entry and innovation support services
We will continue to operate the Ofgem Innovation Link service, offering support on energy regulation to businesses looking to launch new products, services or business models. But recognising the circumstances, we may take longer than usual to respond to requests for feedback.
We will also delay until July 2020 at the earliest, the launch of the expanded innovation sandbox service.
Page history
- First published: 16 April 2020
- Last updated: 16 April 2020