NGET licence modification consultation Large Onshore Transmission Investment
- Statws yr ymgynghoriad:
- Closed (with decision)
- Dyddiad cyhoeddi:
- Closed date:
- Topic:
- Electricity transmission, Energy network price controls
- Sub Topic:
- Transmission price control 2021 to 2026 (RIIO-T2)
- Sector diwydiant:
- Transmission Network
- Math o drwydded:
- Electricity Transmission Licence
Decision:
At RIIO-ET2 Final Determinations, National Grid Electricity Transmission (NGET) were provided funding in its baseline allowance to deliver substation works at the Melksham substation to connect a customer at the Hinkley Point C nuclear power station, with a delivery date in its electricity transmission licence of 31 December 2024.
Due to delays completing Hinkley Point C by the developer, NGET has postponed completion of the Melksham substation works until 2028 to align with the revised forecast completion date.
This is a statutory consultation to modify the delivery date in Special Condition 3.13 Large Onshore Transmission Investments Re-opener of NGET’s electricity transmission licence.