NGET licence modification consultation Large Onshore Transmission Investment

Statws yr ymgynghoriad:
Closed (with decision)
Dyddiad cyhoeddi:
Closed date:
Topic:
Electricity transmission, Energy network price controls
Sub Topic:
Transmission price control 2021 to 2026 (RIIO-T2)
Sector diwydiant:
Transmission Network
Math o drwydded:
Electricity Transmission Licence

Decision:

At RIIO-ET2 Final Determinations, National Grid Electricity Transmission (NGET) were provided funding in its baseline allowance to deliver substation works at the Melksham substation to connect a customer at the Hinkley Point C nuclear power station, with a delivery date in its electricity transmission licence of 31 December 2024.  

Due to delays completing Hinkley Point C by the developer, NGET has postponed completion of the Melksham substation works until 2028 to align with the revised forecast completion date.

This is a statutory consultation to modify the delivery date in Special Condition 3.13 Large Onshore Transmission Investments Re-opener of NGET’s electricity transmission licence.