Search

Draft Determinations on RIIO-2 Re-opener Applications 2025: Electricity Transmission Medium Sized Investment Projects

Math o gyhoeddiad:
Consultation
Last updated:
Closed date:
Status:
Closed (with decision)
Topic:
Electricity transmission
Show all updates

We are consulting on our Draft Determinations and draft direction for five Electricity Transmission Medium Sized Investment Project applications.

Details of outcome

We consulted on our assessment of the application from National Grid Electricity Transmission (NGET) for additional allowances for five projects submitted using the Medium Sized Investment Projects (MSIP) re-opener mechanism between 10 December 2025 and 19 January 2026. Following our review of the responses to our consultation, we are now publishing our Final Determinations for these five MSIP projects.

Read the full outcome

RIIO-2 NGET MSIP Re-opener Applications 2025 Final Determinations [PDF, 186.05KB]
RIIO-2 NGET MSIP Re-opener Applications 2025 Consultation Responses [ZIP, 2.67MB]

Original consultation

Consultation description

As part of the RIIO-2 price control, network companies can apply for additional allowances via re-opener mechanisms. We are consulting on our proposals following our assessment of five Medium Sized Investment Project (MSIP) applications submitted by National Grid Electricity Transmission (NGET) in January 2025.

Who should respond

We would like views from people with an interest in electricity transmission networks. We would also welcome responses from other stakeholders and the public.

How to respond

Submit your responses by 19 January 2026 by emailing reopenerconsultations@ofgem.gov.uk.

All updates

02 March 2026: Added consultation responses and updated consultation status to 'closed with decision'