RIIO-2 Re-opener Applications 2025: Electricity Transmission, Electricity Distribution and Gas Distribution

Publication type:
Consultation
Status:
Closed (with decision)
Publication date:
Closed date:
Topic:
Energy network price controls
Subtopic:
Electricity distribution price control 2023 to 2028 (RIIO-ED2), Gas distribution price control 2023 to 2028 (RIIO-GD2), Transmission price control 2021 to 2026 (RIIO-T2)
Industry sector:
Transmission Network,
Distribution Network

Ofgem’s Final Determinations for various project funding requests from Gas and Electricity network companies under the RIIO-2 re-opener uncertainty mechanisms.

Details of outcome

As part of the RIIO-2 price control, network companies can apply for additional allowances via re-opener uncertainty mechanisms. Up to January 2025, we received re-opener applications across various uncertainty mechanisms from Electricity Transmission, Electricity Distribution and Gas Distribution network companies. We consulted on our Draft Determination on 18 July 2025.  

Our decisions, having taken account of all consultation responses, are set out in these Final Determinations.  Alongside these Final Determinations, we have issued directions setting out relevant outputs and allowance adjustments.  

Read the full outcome 

RIIO-2 Re-opener Applications 2025 Final Determinations: Overview Document [PDF, 450.74KB]
RIIO-2 Re-opener Applications 2025 Final Determinations: ED Annex [PDF, 408.92KB]
RIIO-2 Re-opener Applications 2025 Final Determinations: ET Annex [PDF, 457.19KB]
RIIO-2 Re-opener Applications 2025 Final Determinations: GD Annex [PDF, 421.45KB]
RIIO-2 Reopener Applications 2025: GD direction [PDF, 168.79KB]
RIIO-2 Reopener Applications 2025: Cadent NZASP direction [PDF, 148.61KB]
RIIO-2 Re-opener Applications 2024: Cadent Diversions direction - REDACTED [PDF, 236.41KB]
RIIO-2 Reopener Applications 2025: SSEH Hebrides and Orkney direction [PDF, 121.80KB]
RIIO-2 Re-opener Applications 2025 FD: Datafile [XLSX, 421.33KB]
RIIO-2 Re-openers DD 2025 Responses [ZIP, 19.22MB]

Original consultation

Consultation details

As part of the RIIO-2 price control, network companies can apply for additional allowances via re-opener mechanisms. We are consulting on our proposals following our assessment of a number of applications from nine network companies in the electricity transmission, electricity distribution, and gas distribution sectors.  These applications were received up to January 2025 and were submitted under the following re-opener mechanisms:  

  • Medium Sized Investment Projects (MSIP)
  • Large Onshore Transmission Investment (LOTI)
  • Hebrides and Orkney Whole System Uncertainty Mechanism (HOWSUM)
  • Load Related Expenditure Re-opener (LREt)  
  • Health and Safety Executive (HSE) Policy Re-opener
  • Specified Streetworks Costs Re-opener
  • Net Zero Pre-Construction Work and Small Net Zero Projects (NZASP) Re-opener 

We are consulting on our Draft Determinations and draft directions for these applications. 
 
We would like views from people with an interest in electricity transmission, electricity distribution and gas distribution networks. We would also welcome responses from other stakeholders and the public.