Decision to modify National Grid Gas Plc's Gas Transporter Licence to add new National Transmission System exit points
Decision
We have decided to modify Special Condition 9.13 (Capacity Requests, Baseline Capacity and Capacity Substitution) of National Grid Gas plc’s gas transporter licence.
Our statutory consultation published on 13 July 2022 proposed adding 4 new exit points to the National Transmission System. These were: "Grain North Power Station,” “Hirwaun Power Station,” “Progress Power Station” and “Millbrook Power Station."
We received one response to our statutory consultation from National Grid Gas plc, which was non-confidential and is published below.