Decision on the System Test Plan

Decision
Publication date
Industry sector
Transmission Network
Licence type
Electricity Transmission Licence

 

On 21 December 2019, we received a proposal for a System Test Plan (the “test plan”) for Great Britain (“GB”) from the Electricity System Operator (“ESO”) developed in accordance with Article 43(2) of Commission Regulation (EU) 2017/2196 (the “NCER Regulation”). This proposal was submitted for our approval in accordance with Article 4(2) of the NCER Regulation.



This letter sets out our decision to approve the proposed test plan for GB as submitted by the ESO and also outlines any necessary next steps that must be taken.