GDF Suez - Capacity Market Rules change proposal 2

Publication type:
Change Proposal
Status:
Closed (rejected)
Publication date:
Last updated:

This proposal from GDF Suez would make an addition to Rule 12.2 (Monitoring of construction progress of Prospective Generating CMUs). Rule 12.2 requires the CMU report to the Delivery Body every six months on progress made against the Construction Plan until the Substantial Completion Milestone. The proposed change would require an independent audit of these reports. Unsatisfactory audit findings would result in the CMU being entitled only to a one-year capacity agreement and not being permitted to bid as a Refurbishing CMU in future auctions.

Proposal rules area

Monitoring

Proposal organisation

GDF Suez