Search

BEIS - Capacity Market Rules CP236

Publication type:
Change Proposal
Status:
Closed (accepted)
Publication date:
Last updated:

This proposal seeks to amend the Rules to ensure Prospective CMUs cannot delay their Metering Test having met their Minimum Completion Milestone or Substantial Completion Milestone and receive Capacity Payments whilst potentially operating with non-compliant metering. The proposed amendments also clarify the timetable for Metering Assessments and Metering Test Certificate submissions for Prospective CMUs.

Proposal rules area

Testing Regime

Proposal organisation

BEIS
Print this page