BEIS - Capacity Market Rules CP236

Publication date:
Last updated:
Change proposal status:
Closed (accepted)
Print this page

This proposal seeks to amend the Rules to ensure Prospective CMUs cannot delay their Metering Test having met their Minimum Completion Milestone or Substantial Completion Milestone and receive Capacity Payments whilst potentially operating with non-compliant metering. The proposed amendments also clarify the timetable for Metering Assessments and Metering Test Certificate submissions for Prospective CMUs.

Proposal rules area

Testing Regime

Proposal organisation

BEIS