Consent for an extension to the timescales for issuing connection offers
Decision
National Grid Electricity System Operator requested the Authority's consent for extension to the timescales for issue of fourteen connection offers, consequential to delayed receipt of information from a transmission owner. This letter contains the Authority's decision to grant consent to an extension for these offers, pursuant to paragraph 5 of standard licence condition C8 of the transmission licence standard conditions.