Consultation on Scottish Power Transmission Ltd's opening asset value for project 'Sloy'

Publication type:
Consultation
Publication date:
Closed date:
20 February 2015
Status:
Closed (with decision)
Topic:
Electricity transmission

Decision:

Project Sloy has been jointly delivered by Scottish Power Transmission and Scottish Hydro Electric Transmission to relieve constraints on the latter’s network. It is funded under the conditions of the Investment for Renewable Generation (TIRG). The outputs associated with Scottish Power Transmission’s work on the project were delivered in 2009/10. This consultation is on our view that the revenue Scottish Power Transmission receives for the five years following construction remain at £19.366 million, which is the level set by our determination to provide additional funding for the project in November 2010.

Respond name

Saad Mustafa

Respond telephone