Final Decision: National Grid Grain LNG's application for an exemption from regulated third party access for Isle of Grain phase 4

Decision
Publication date
Industry sector
Generation and Wholesale Market

This letter sets out Ofgem’s final decision regarding GLNG’s application for an exemption from regulated third party access (rTPA) for Isle of Grain Phase 4.

This exemption was revoked on 4 June 2015, as construction of this phase of the facility had not started within 2 years of the exemption being approved.