Robin Hood Energy Limited: Final Order

Orders
Closed

Publication date

Closed date

Company

Licence type

Electricity Supply Licence

Scheme name

RO

On 1 October 2019, the Authority published its notice of proposal to issue a Final Order (FO) on Robin Hood Energy Ltd in accordance with Section 25(1) of the Electricity Act 1989 (EA89).

The particular behaviour of concern giving rise to the proposed FO was that Robin Hood Energy Ltd failed to meet its Renewables Obligations (RO), by failing to produce Renewables Obligation Certificates (ROC) to the Authority by 1 September 2019, or to make payments as an alternative by 31 August 2019, sufficient to discharge its RO. Robin Hood Energy Ltd subsequently failed to provide robust assurance that it could and would be in a position to make the necessary payment, including applicable interest, by the late payment deadline of 31 October 2019.

The Authority noted the representations received in the context of the consultation undertaken pursuant to section 26(1) of the EA89.

Robin Hood Energy Ltd made full payment of its RO for 2018-19, including all applicable interest, thus ensuring compliance with its RO for 2018-19.

Therefore, on 29 October 2019, the Authority made a decision not to make a FO.