Request for amendment of proposed arrangements for more than one Nominated Electricity Market Operator in a Bidding Zone
Decision
Publication date
Industry sector
Generation and Wholesale Market
On 11 April 2016, we received two proposals developed by Transmission System Operators (TSOs) for arrangements concerning more than one Nominated Electricity Market Operator (NEMO) in a bidding zone. These proposals were submitted in accordance with Articles 45 and 57 of the guideline on Capacity Allocation and Congestion Management (CACM) and consider the day-ahead and intraday timeframes respectively.
This letter sets out our decision to request an amendment and for the TSOs to resubmit the proposals to us.