- Publication date
- 2nd October 2018
- Information types
- Guidance
- Policy areas
- Environmental programmes
- ECO
This Boiler Assessment Checklist is designed to assist operatives in assessing whether a boiler should be repaired, replaced or upgraded alongside a primary insulation measure.
The ECO3 Order commenced on 3 December 2018 and runs until 31 March 2022. These documents apply to any measures delivered from 1 October 2018.
For measures installed before this date, suppliers should refer to this document.
Amendments – 10 October 2018 (Version 3.2)
The ECO3 Boiler Assessment Checklist was republished on 10 October 2018 to reflect a number of minor changes which should improve the overall usability of the document.
Amendments - 15 February 2019 (Version 3.3)
This document was republished to account for First Time Central Heating measures under ECO3. A new section was created to capture occasions where heating controls (TRVs) cannot be installed as part of a measure. Suppliers and installers should use version 3.3 of the ECO3 Boiler Assessment Checklist.
Amendments – 17 January 2020 (Version 3.4)
This document was republished to reflect a number of minor changes which should improve the overall usability of the document. Appendix 1 was updated to record the costs associated with boiler repairs and replacements.
Amendments - 23 January 2020 (Version 3.5)
This document was republished with minor formatting corrections.