Decision on RIIO-ED1 price control reopeners (submissions made during May 2019 window)

Decision

Publication date

Industry sector

Distribution Network

We received applications from all six electricity distribution network operators (DNOs) during the May 2019 reopener window. In these applications, the DNOs requested an adjustment to allowances, related to the following uncertain cost categories:

  • High Value Project Costs
  • Rail Electrification Costs
  • Enhanced Physical Site Security Costs
  • Specified Streetworks Costs.

We have now made our final decision on these reopener applications.

We received consultation responses from eight stakeholders: Citizens Advice, Centrica, Electricity Northwest Limited (ENWL), Northern Powergrid (NPg), SP Energy Networks (SPEN), Scottish and Southern Electricity Networks (SSEN), UK Power Networks (UKPN) and Western Power Distribution (WPD). Non-confidential versions of these responses are published on our consultation page and can be found here.

As part of Phase 1 of our stakeholder consultation process, we published non-confidential versions of network company applications, and sought early feedback from stakeholders in an informal consultation. Further information on Phase 1 of our consultation process can be found here.