OFTO Tender Round 2

Resources, guidance and details for OFTO Tender Round 2

OFTO Tender Round 2 started in November 2010 and was divided into two tranches, A and B. Tranche B started in December 2012. Tender Round 2 enabled prospective bidders to compete to own one or more of the offshore transmission assets associated with:

  • London Array
  • Lincs
  • Gwynt y Môr
  • West of Duddon Sands

Tender Round 2 publications

The following publications relate to the tender and award process for Tender Round 2:

Offshore transmission assets

London Array

OFTO transmission assets value: £444m 

Current status: Licensed OFTO
Installed capacity: 630 MW
Developed by: DONG, E.on and Masdar 

Operator: Blue Transmission

Lincs

OFTO transmission assets value: £307.7m 

Current status: Licensed OFTO
Installed capacity: 270 MW
Developed by: DONG, Centrica, and Siemens

Operator: Transmission Capital Partners

Gwynt y Môr

OFTO transmission assets value: £351.9m 

Current status: Licensed OFTO
Installed capacity: 574 MW
Developed by: RWE, Stadewerke München and Siemens

Operator: Balfour Beatty

West of Duddon Sands

OFTO transmission assets value: £268.9m 

Current status: Licensed OFTO
Installed capacity: 388 MW
Developed by: DONG and Scottish Power Renewables

Operator: Blue Transmission