Grid connections delays: inquiry into phase 1 projects to drive delivery and accountability
- Publication type:
- News
- Publication date:
- Topic:
- Electricity transmission
- Subtopic:
- Connections
Connections reform has removed significant speculative capacity from the connections queue and created a more credible pipeline of projects. This will reduce the amount of network infrastructure Great Britain needs to build, helping to control costs for consumers. However, the majority of projects in the reformed queue are seeing delays rather than advancements compared to their pre-reform position. We share the frustration of customers whose projects have moved backwards in the queue, in some cases materially.
We are disappointed with the emerging outcomes for customers at the end of Phase 1 and are therefore increasing our regulatory scrutiny accordingly. We want to understand the root causes of these delays including how the picture may differ across network companies. We are therefore launching an urgent inquiry into why grid connection offers for many protected and Phase 1 projects have been delayed relative to their pre-reform connection offer dates, despite a clearing-up of the queue.
Our first focus is delivery. As a country, the amount we need to connect to the network is doubling every few years. Meeting this challenge requires a step change in delivery on all fronts. We are working with the Department for Energy Security and Net Zero (DESNZ), and we are asking networks and the National Energy System Operator (NESO) to identify what can be done to improve outcomes and accelerate dates wherever possible.
Alongside this, we want to radically improve transparency. Connecting parties must be given the information they need to make informed choices on the best approaches for their projects. We are therefore asking NESO and networks to focus on four immediate areas:
- Better data - We are working with DESNZ, NESO and networks to openly share a clear picture of connection dates, updated as offers are issued, and to understand why dates have changed.
- Analysis behind the offer - NESO will rapidly publish more information on Construction Planning Assumptions and, with industry, bring forward rule changes to make the connections queue more transparent. This should allow projects to better understand their offers and engage with networks on the specifics of the works needed to connect their project to the grid.
- Ready and needed queue - We will continue to rapidly progress work on additional measures to ensure the queue remains ready and needed, focused on financial commitments for over-subscribed technologies (notably batteries); and for speculative and non-viable data centre projects.
- Milestones are managed - Now that offers are being accepted, NESO will closely monitor performance against queue milestones and intervene to ensure that projects that don’t make sufficient progress don’t remain in the queue.
Alongside these immediate actions, we are taking action to improve the connections experience of customers by:
- Strengthening customer service - Through our Transforming the Connections Experience programme, we have set out clearly our network reforms to give customers clearer information, more transparent offers and better communication throughout the connections process. We have been clear on the direction of travel in our three consultations to date, and strongly recommend networks work towards making these improvements straight away.
- Strengthening customer protection - We are exploring stronger arrangements for automatic compensation to customers where networks cause delays to connections and see no reason why connection agreements cannot contain such provisions now.
- Expanding developer self-build - We will implement reforms that allow connecting customers to self-build and transfer their transmission connections and enable ownership of transmission assets through an independent transmission owner licence. We expect positive, proactive engagement from transmission owners to make these reforms a success and allow customers with existing offers to benefit.
Finally, we will drive accountability throughout the system. Not every delay has the same cause, and we will examine the evidence carefully. But complexity cannot be allowed to obscure poor performance. We intend to use the RIIO-3 connections incentive to reward or penalise network companies based on their performance. We will consult on setting the baseline for this incentive in December, against which network performance will be measured.
Our inquiry will establish transparently why grid connection offers for protected and Phase 1 projects have been delayed. We will also identify lessons that must be learned for future connection windows. Where this inquiry reveals a material breach of licence obligations by either NESO or the network companies, we will not hesitate to take enforcement action.
We intend to make our scrutiny transparent. We will develop more frequent reporting of network delivery and connections performance, starting with the Infrastructure Progress Report in February where we will publish the data on connection outcomes.
The success of connections reform will ultimately be judged by whether it delivers better outcomes for customers, not simply a shorter queue. Viable projects should receive the earliest connection date that is efficient and deliverable, be able to understand and rely on the basis for that date, receive clear and timely information, and be confident that under-delivery will be challenged. We will continue to work with government and hold NESO and the network companies to account for delivering that outcome at pace.