Draft determinations for the RIIO-ET3 Load Re-opener May 2026 submission window
- Publication type:
- Consultation
- Publication date:
- Last updated:
- Closed date:
- Status:
- Closed (with decision)
- Topic:
- Energy network price controls,
- Electricity transmission
- Subtopic:
- RIIO-T3: transmission price control 2026 to 2031
Proposed Load Re-opener decisions on May 2026 applications.
Details of outcome
The Load Re-opener enables electricity transmission owners (ETOs) to request additional allowances for new load projects which were not funded or only partially funded at the start of the Price Control Period as part of our RIIO-3 Final Determinations. It provides flexibility for ETOs to deliver necessary network infrastructure at pace, whilst protecting consumers from unnecessary costs.
We received 30 applications from ETOs in the May 2026 Load Re-opener submission window, and have assessed 29 of those.
We consulted on our proposed decisions between 27 August 2026 and 24 September 2026. We received nine responses to this consultation, which we have now considered, and have reached our final decisions.
Our Final Determinations sets out our decisions including associated additional allowances and reasoning for any adjustments to ETO requests.
Read the full outcome
Original consultation
Description
The Load Re-opener enables electricity transmission owners (ETOs) to request additional allowances for new load projects which were not funded or only partially funded at the start of the price control period as part of our RIIO-3 final determinations. It provides flexibility for ETOs to deliver necessary network infrastructure at pace, whilst protecting consumers from unnecessary costs.
We have assessed 30 applications made by ETOs in the May 2026 Load Re-opener application window. Our draft determinations sets out our proposed decisions including associated additional allowances and reasoning for any adjustments to ETO requests.
Who should respond
We would like views from people with an interest in the energy transition and network infrastructure. We particularly welcome responses from:
- ETOs
- consumer groups
- other interested industry parties
Consulation documents
All updates
6 November 2026 published consultation decision with final determinations