This decision sets out our new approach to the timelines and incentives framework as applied to the Third Cap and Floor Window for Electricity Interconnectors. To protect consumers from undue delays and maintain the risk-reward balance between consumers and developers, our changes are centred around the treatment of interconnector project delivery delays.
We are introducing:
Separately we have in parallel published decisions on the below, which form part of the wider timelines and incentives framework applied to the Third Cap and Floor Window for Electricity Interconnectors:
The Policy Decision document: Pre-Operational Force Majeure requests made in the Third Cap and Floor Window for Interconnectors around pre-FPA decision.
The new standard condition (SLC) 26B: Pre-Operational Force Majeure requests made in the Third Cap and Floor Window for Interconnectors around post-FPA decision.