Sealink: Early Construction Funding consultation

Publication type:
Consultation
Status:
Closed (with decision)
Publication date:
Last updated:
Closed date:
Topic:
Electricity transmission
Subtopic:
Accelerated Strategic Transmission Investment (ASTI)
Industry sector:
Transmission Network
Licence type:
Electricity Transmission Licence
Show all updates

Details of outcome

This document confirms our decision to approve Early Construction Funding (ECF) for the Sea Link (NOA code SCD1) electricity transmission project. This decision is taken in line with National Grid Electricity Transmission’s (NGET) electricity transmission licence (the Licence), Special Condition (SpC) 3.41 ‘Accelerated strategic transmission investment Re-opener and Price Control Deliverable term (ASTIRt)’.

Read the full outcome

Sea Link: decision on Early Construction Funding and Modification to special conditions of the electricity transmission licence [PDF, 181.94KB]
Sea Link: consultation responses [PDF, 9.30MB]
Modification of the Special Condition (SpC) 3.41 of the electricity transmission licence held by National Grid Electricity Transmission Plc [PDF, 364.58KB]

Background

The British Energy Security Strategy set out the Government's ambition to connect up to 50GW of offshore generation to the electricity network by 2030. In December 2022 we introduced a new ASTI framework that will assess, fund and incentivise the accelerated delivery of large strategic transmission projects required to deliver on the Government's ambition.

Original consultation

This consultation sets out our Early Construction Funding assessment of the Sea Link (SCD1) project under the Accelerated Strategic Transmission Investment (ASTI) re-opener. 

Respond name

Amy Freund

All updates

19 November 2025 Decision document, consultation responses and licence modification added