Long Duration Electricity Storage: Draft Special Licence Conditions
- Publication type:
- Call for input
- Publication date:
- Last updated:
- Closed date:
- Status:
- Closed
- Topic:
- Long duration electricity storage
We are seeking views on a working draft of the proposed special licence conditions for the Long Duration Electricity Storage (LDES) cap and floor scheme.
Details of outcome
We received 40 responses in total. These were used these to inform our minded-to-positions on the draft framework for the long duration electricity storage (LDES) special licence conditions.
We have not yet made any final decisions at this stage. However, we are seeking further views on these minded-to-positions in our latest call for input.
Read the full outcome
Read the full outcome in our Long duration electricity storage window 1: revised special licence conditions call for input.
This file may not be not fully accessible. If you require an alternative format, please email ldes@ofgem.gov.uk.
Original call for input
Call for input description
This call for input forms part of early, non-statutory engagement and is intended to help us refine the drafting, structure and operability of the licence conditions before launching a statutory consultation planned for Q2 2026.
We welcome feedback on the full draft, with a particular focus on specific policy areas and drafting points where stakeholder input is most valuable at this stage.
Who should respond
While this consultation is particularly relevant to LDES projects applying under the first application window, we also welcome input from stakeholders, including industry participants, energy experts, and members of the public.
Your feedback will help us refine the draft special licence conditions ahead of the statutory consultation.
All updates
13 April 2026 added clarification log.
21 July 2026 added outcome for call for input and non-confidential responses.