Update on our work to resolve issues in the market for new connections to electricity distribution networks and informal licence consultation

Publication date
12th May 2015
Closing date
9th June 2015
Policy areas
Status

This letter -

  • Consults on a draft of our proposed new licence condition to be inserted into the standard conditions of the distribution licence (see PART 1 – the new licence condition).
  • Explains how we will assess the suitability of the Code of Practice (CoP) that the distribution network operators (DNOs) propose (see PART 2 – the Code of Practice).
  • Details our decisions on the minimum requirements for the CoP (see also PART 2 – the Code of Practice).

Please send us your responses to our consultation on the licence condition by 9 June 2015 to connections@ofgem.gov.uk.