Delta Gas and Power Limited: Final Order

Orders
Closed
Publication date
Closed date
Licence type
Electricity Supply Licence
Scheme name
RO

On 1 October 2019, the Authority published its notice of proposal to issue a Final Order (FO) on Delta Gas and Power Ltd in accordance with Section 25(1) of the Electricity Act 1989 (EA89).

The particular behaviour of concern giving rise to the proposed FO was that Delta Gas and Power Ltd failed to meet its Renewables Obligations (RO), by failing to produce Renewables Obligation Certificates (ROC) to the Authority by 1 September 2019, or to make payments as an alternative by 31 August 2019, sufficient to discharge its RO. Delta Gas and Power Ltd subsequently failed to provide robust assurance that it could and would be in a position to make the necessary payment, including applicable interest, by the late payment deadline of 31 October 2019.

The Authority noted the representations received in the context of the consultation undertaken pursuant to section 26(1) of the EA89.

Delta Gas and Power Ltd made full payment of its RO for 2018-19, including all applicable interest, thus ensuring compliance with its RO for 2018-19.

Therefore, on 29 October 2019, the Authority made a decision not to make a FO.