Market-wide Half Hourly Settlement change request CR067
- Publication type:
- Decision
- Publication date:
- Topic:
- Electricity supply
- Subtopic:
- Market-wide half-hourly settlement (MHHS)
Our decision on change request CR067, which proposes to split Market-wide Half Hourly Settlement (MHHS) milestone M15 into M15a, individual supplier migration, and M15b, overall migration completion.
Details
The proposal retains the existing M15 baseline date of 7 May 2027 for both milestones.
Under the current MHHS Implementation Plan, the M15 Milestone is defined as ‘Full Transition Complete’ and is described as “the completion of implementation activities and the conclusion of the 18-month migration period”. This description incorporates two distinct elements: the deadline for individual suppliers to complete the migration of their Meter Point Administration Numbers (MPANs) to MHHS, and the overall migration of all MPANs when 100% of energy is settled under the new MHHS arrangements.
Recent decisions taken under BSC and Programme governance make provisions for suppliers, under certain conditions, to migrate after the baselined date with an exemption or whilst subject to registration restrictions. Consequently, while the Programme is still planning on the basis that all suppliers will have completed their migration by 7 May 2027, the Programme considers that a change is required so the Programme has a clear and robust basis for managing the supplier-level compliance deadline and the industry-level transition completion point.
CR067 would create separate milestones. These are M15a, marking completion of the 18-month migration period and triggering registration restrictions for suppliers where applicable, and M15b, representing the point at which all suppliers have completed migration and 100% of energy is settled under MHHS arrangements.
Outcome
Ofgem agrees that the Change Request would establish a clear distinction between the compliance deadline for individual suppliers and the overall completion of migration at industry level. This would provide a sound basis for monitoring and reporting progress against all scenarios, including where one or more suppliers are subject to exemptions or registration restrictions. On that basis, we have decided to approve CR067.
In doing so, Ofgem wishes to underline that 7 May 2027 remains the compliance deadline for each supplier to migrate its own portfolio of MPANs. We expect all suppliers to ensure that they allocate the resources necessary to achieve this and so facilitate the timely completion of MHHS migration at industry level.