Approval of the modified Access Rules for the Nemo Link interconnector

Publication type:
Decision
Publication date:
Topic:
Electricity interconnectors

On 14 August 2019, Nemo Link Limited (NLL) submitted updated Access Rules for the Nemo Link interconnector to the Authority for approval.

The Access Rules set out the terms and conditions for access to, and including use of, the interconnector.

The modifications are to the Access Rules that are applicable as long as the UK remains within the Internal Energy Market.

We have decided to approve the modified Access Rules proposed by NLL on the basis that they achieve the relevant Access Rules objectives. These modified Access Rules will enter into force on 14 November 2019 to facilitate the  first Nemo Link intraday auctions.

This letter sets out our decision to approve the modified Access Rules for the NEMO Link interconnector, including an outline of the necessary next steps. This letter also contains a Direction approving the modified Access Rules.