Consultation: 3 SPT 2023 MSIP applications
- Consultation status:
- Closed (with decision)
- Publication date:
- Closed date:
- Industry sector:
- Transmission Network,
- Distribution Network
Decision:
Related links
As part of the RIIO-2 price control, electricity transmission networks have the Medium Sized Investment Project (MSIP) re-opener for projects that meet certain conditions and cost less than £100m. In the January 2023 reopener window, SP Transmission (SPT) submitted eight applications, of which five are initial needs case submissions and three are full applications. We have already published a consultation on our assessment of the five first stage applications on 28 June 2023. This document summarises our assessment of the three full applications as listed below.
- Coalburn Supergrid Transformer Number 4
- Constraint Management Pathfinder - Line End Open (LEO) and Operational Intertrip Scheme (OTS) Modifications
- Wishaw - Eccles - Torness - Smeaton OTS