CMP472 Connection and Use of System Code (CUSC) proposed changes

Publication type:
Code modification
Publication date:
Topic:
Electricity generation,
Electricity transmission

Outcome of proposed changes to Connection and Use of System Code, CMP472 Large Embedded Generators Original Red Line Boundary Sharing Without Customer Consent.

Details of outcome

On 11 September 2026, the Final Modification Report for Connection and Use of System Code (CUSC) modification proposal CMP472 was submitted to Ofgem for decision. We have decided to approve this proposal.

Start date

The proposal will be implemented on 11 December 2026.

Code modification description

CMP472 introduces a change to the CUSC requiring the National Energy System Operator (NESO) to share Original Red Line Boundary (ORLB) information submitted by Large Embedded Generators (LEGs) with the relevant distribution network operator (DNO), rather than requiring the applicant’s consent.

Under current arrangements, consent being delayed or withheld could allow projects with invalid or non-compliant contracts to progress before issues are identified. This could lead to avoidable network design, assessment and queue management activity. Removing the consent requirement will enable DNOs to identify these issues earlier and reduce the need for subsequent rework.