CMP376: Inclusion of Queue Management process within the CUSC

Publication type:
Decision
Publication date:
Topic:
Energy codes
Subtopic:
Connection and use of system code (CUSC)
Industry sector:
Transmission Network,
Distribution Network

We have approved CMP376, specifically WACM7. This will see a queue management process applied to new and existing Construction Agreements, with associated termination powers provided to National Grid ESO where projects fail to meet set milestones. These changes to the CUSC will take effect from November 2023.