Statutory Consultation to modify Special Condition 6F (Baseline Generation Connection Outputs and Generation Corrections volume driver) (“SpC 6F”) of Scottish Hydro Electric Transmission plc’s (“SHET”) electricity transmission licence

Consultation
  • Upcoming
  • Open
  • Closed (awaiting decision)
  • Closed (with decision)

Publication date

Closing date

Industry sector

Transmission Network

Decision

We believe logical errors in SpC 6F are reducing transparency about the allowance calculations. The errors primarily cause issues with the calculation of interim allowances rather than final post-reconciliation values for actual capacity delivery. To promote consistency, for this consultation we have reviewed and are proposing changes to all the algebra in SPC SpC 6F.