Decision on proposed licence modifications to special licence condition 3J of the electricity transmission licence
Decision
Decision on our proposed modifications to special condition 3J (Transmission Investment for Renewable Generation - TIRG) of the electricity transmission licence.
The modification corrects the calculation of the post-construction allowed incentive revenues for each project covered by the TIRG arrangements.