We have decided to modify Part F of Special Condition 5G (Determination of Incremental Obligated Exit Capacity volume and the appropriate revenue drivers to apply) and Part F of Special Condition 5F (Determination of Incremental Obligated Entry Capacity volume and the appropriate revenue drivers to apply) of National Grid Gas plc’s (NGG) gas transporter licence.
Our statutory consultation published on 25 October 2018 proposed adding two new exit points, “Keadby 2 Power Station” and “Eggborough Power Station”. Additionally proposing to add one new entry point, "Murrow".
We are also proposing that we do not consider any of these points to be relevant points under Article 18(4) of the EU Gas Regulation.
The Authority's determination can be found in the attached notice.