Scottish Hydro Electric Transmission Plc

We have awarded funding for three Scottish Hydro Electric Transmission Plc projects.

New Suite of Transmission Structures (NeSTS) - 2015

This project aims to develop a new suite of overhead line supports that are smaller, better for the environment and could result in financial savings for customers.

Modular Approach to Substation Construction - 2014

This project aims to develop and trial a modular approach to substation construction which integrates substation components with other innovations in civil works and cabling.

Multi-Terminal Test Environment (MTTE) for High Voltage Direct Current Systems - 2013

This project aims to establish a facility to demonstrate and test multi-terminal and multi-vendor High Voltage Direct Current transmission solutions.

You can find further information on each project and related documents under the publications and updates feed below.

Publications and updates

  • Published: 12th Feb 2015
  • Reports and plans
  • 1 Associated documents
This is the Six Monthly Report, delivered by Scottish Hydro Electric Transmission Plc on their Electricity NIC project: Multi-Terminal Test Environment ( MTTE ) for High Voltage Direct Current Systems.

  • Published: 14th Jan 2015
  • Open letters and correspondence
  • 1 Associated documents
This direction sets the conditions of funding for Scottish Hydro Electric Transmission's Project - Modular Approach to Substation Construction (MASC).

  • Published: 24th Nov 2014
  • Reports and plans
  • 4 Associated documents
These are all the non-confidential documents submitted by Scottish Hydro Electric Transmission to the Electricity NIC for the project entitled Modular Approach to Substation Construction on which our decision is based.

  • Published: 15th Aug 2014
  • Reports and plans
  • 1 Associated documents
This is the Six Monthly Report, delivered by Scottish Hydro Electric Transmission Plc on their Electricity NIC project: Multi-Terminal Test Environment (MTTE) for High Voltage Direct Current Systems

  • Published: 8th Jan 2014
  • Reports and plans
  • 1 Associated documents
This direction sets the conditions of funding for Scottish Hydro Electric Transmission’s Network Innovation Competition Project – Multi Terminal Test Environment for HVDC Systems.

  • Published: 29th Nov 2013
  • Reports and plans
  • 4 Associated documents
These are all the non-confidential documents submitted by SHE Transmission to the Electricity Network Innovation Competition. These are for the project entitled Multi-Terminal Test Environment (MTTE) on which our decision is based.

Pages