Energy Company Obligation public reports and data

Energy Company Obligation public reports and data

Energy Company Obligation 3 interim measures

The Energy Company Obligation 4 order commenced on 27 July 2022 and will run to 31 March 2026. Measures delivered between 1 April 2022 to 26 July 2022 will contribute to Energy Company Obligation 4 delivery and will be known as Energy Company Obligation 3 Interim measures as they are delivered in accordance with Energy Company Obligation 3 regulations.

Suppliers had to notify us of any Energy Company Obligation 3 interim measures installed between 1 April 2022 and 26 July 2022 by the end of September 2022.

Any Energy Company Obligation 4 measures completed between 27 July 2022 and 31 July 2022 also had to be notified by the end of September 2022.

Any measures completed on or after 1 August 2022 must be notified by the end of the month following the month in which installation of a measure was completed.

Progress towards obligation

Progress towards Phase 1, 2 and 3

To achieve its ECO obligations, a supplier must install measures that qualify under the scheme and deliver annual bill savings for the household.

ECO4 sets a main obligation called the Home Heating Cost Reduction Obligation (HHCRO), which requires energy suppliers to achieve a total of £224.3 million in annual bill savings for domestic premises by 31 March 2026.

The obligation is divided between energy suppliers based on their respective shares of the domestic gas and electricity market.

A supplier meets its obligations under ECO4 by promoting qualifying actions (‘measures’) at eligible domestic premises, and must do so in full no later than 31 March 2026.
           
The overall obligation period for ECO4 runs from the commencement of the ECO4 Order on 27 July 2022 to 31 March 2026 and is split into four phases:

•    Phase 1: 27 July 2022 to 31 March 2023
•    Phase 2: 1 April 2023 to 31 March 2024
•    Phase 3: 1 April 2024 to 31 March 2025
•    Phase 4: 1 April 2025 to 31 March 2026

A supplier’s total obligation is determined by adding together their obligations for each phase. They must meet their total obligation by the end of 31 March 2026.

Measures

Notified Energy Company Obligation 4 measures by category

The table below shows the measures submitted to Ofgem as of 6 May 2025.

This does not include Energy Company Obligation 4 measures that have been notified as exemption measures. For further details on exemption measures, please refer to our Energy Company Obligation (ECO4) Guidance: Delivery.

Measure Type  Surplus actions  ECO3 Interim  ECO4  Total 
Boiler - Repair of an efficient heating system 
Boiler - Replacement of a broken efficient heating system  1,847  1,804  308  3,959 
Boiler - Upgrade of an efficient heating system to a renewable heating system  25,356  25,356 
Boiler - Upgrade of an inefficient heating system  60,253  60,258 
Boiler - Upgrade to Unknown* 
Cavity Wall Insulation  13,724  12,723  23,794  50,241 
District Heating Connection   1,316  1,318 
ESH - Repair of a broken efficient ESH 
ESH - Replacement of a broken efficient ESH 
ESH - Upgrade of an inefficient heater  1,749  1,724  5,704  9,177 
First time central heating to a non-renewable heating system  2,775  1,802  11,922  16,499 
First time central heating to a renewable heating system  32  72  10,276  10,380 
First time central heating to an unknown heating system* 
Heating controls  15,809  5,169  373,796  394,774 
Loft Insulation  11,883  4,039  85,600  101,522 
Other Insulation**  100  35  4,159  4,294 
Park Home Insulation  29  805  834 
Room-in-roof Insulation  946  290  14,403  15,639 
Solar PV  138  103  43,525  43,766 
Solid Wall Insulation  6,956  1,570  60,794  69,320 
Underfloor Insulation  4,703  896  1,372  6,971 
Grand Total  60,695  30,230  723,387  814,312 

Table commentary

A total of 177,706 Energy Company Obligation 4 projects have been submitted, an increase of 6,133 projects from the previous month.

*A small number of measures have been submitted with an invalid post main heating source for the property, suppliers will be required to update this information

**Other Insulation includes the following measure types – flat and pitched roof insulation, solid floor insulation, window glazing, draught proofing and higher performance external doors. These measures are grouped together given the low delivery volumes.

Percentage of energy company progress towards obligations and cap

Data is accurate as of 6 May 2025. 

Notified delivery refers to measures and projects which suppliers have submitted to the Energy Company Obligation 4 register. The notified percentage will count partial project scores from non-approved measures, where the measures and projects are still undergoing their eligibility review.

Approved delivery refers to those that have passed eligibility reviews to count towards the obligation target. The approved percentage will count full project scores from approved projects. Where a project has been completed but yet to be approved, partial project scores from the approved associated measures are used.

Please note that:

  • due to notification and validation errors, there are measures and projects which do not have scores generated, meaning the current progress figures do not reflect 100% of delivery towards ECO4. As of 6 May 2025, the data shows progress for 95.62% of delivery, therefore actual delivery is likely to be higher
  • progress from approved surplus actions carried over from ECO3 is now reflected in the data

Publications and updates