Decision further to National Grid Electricity Transmission plc’s request for Derogation under Standard Licence Condition C14 (Grid Code) of the Electricity Transmission Licence
Decision
NGET has submitted a derogation request from the obligation for the data required in clauses BC1.4, BC1.A.1.3.1, BC1.A.1.3.2 and BC1.A.1.5 to be submitted at a Grid Supply Point (GSP) level.
This letter sets out our decision to grant the requested derogation. The Direction published alongside this decision letter gives effect to this decision.