Uniform Network Code (UNC498): Amendment to Gas Quality NTS Entry Specification at BP Teesside System Entry Point and UNC502: Amendment to Gas Quality NTS Entry Specification at the px Teesside System Entry Point

Decision

Publication date

UNC498 sought to  facilitate a change to the current contractual Carbon Dioxide limit at the BP Teesside System Entry Point, through modification of a Network Entry Provision contained within the Network Entry Agreement (NEA) between National Grid plc and Amoco (UK) Exploration Company LLC in respect of the CATS Terminal (BP Teeside).

UNC502 sought to facilitate a change to the current contractual Carbon Dioxide limit at the px Teeside System Entry Point, through modification of a Network Entry Provision contained within the Network Entry Agreement ("NEA") between National Grid Gas and px (TGPP) Limited in respect of the px Teeside System Entry Point.

The Authority approved these modifications on 25 September 2015.