Decision further to National Grid Electricity Transmission plc’s request for Derogation under Standard Licence Condition C14 (Grid Code) of the Electricity Transmission Licence
Decision
Publication date
Company
Industry sector
Generation and Wholesale Market
NGET has submitted a derogation request from the obligation for the data required in clauses BC1.4, BC1.A.1.3.1, BC1.A.1.3.2 and BC1.A.1.5 to be submitted at a Grid Supply Point (GSP) level.
This letter sets out our decision to grant the requested derogation. The Direction published alongside this decision letter gives effect to this decision.