Decision further to National Grid Electricity Transmission plc’s request for Derogation under Standard Licence Condition C14 (Grid Code) of the Electricity Transmission Licence

Decision

Publication date

Company

Industry sector

Generation and Wholesale Market

NGET has submitted a derogation request from the obligation for the data required in clauses BC1.4, BC1.A.1.3.1, BC1.A.1.3.2 and BC1.A.1.5 to be submitted at a Grid Supply Point (GSP) level.

This letter sets out our decision to grant the requested derogation. The Direction published alongside this decision letter gives effect to this decision.