Blue Transmission London Array Limited – Direction under paragraph 10 of Amended Standard Condition E12-J4

Publication type:
Decision
Publication date:
Topic:
Offshore electricity transmission

This document outlines the Authority’s decision that a cable failure at Blue Transmission London Array Limited from 9th to 16th September 2016 was not caused by an exceptional event, and provides the reasons for this decision.