Approval of modified Access Rules and Charging Methodology for the IFA Interconnector

Decision

Publication date

Industry sector

  • Transmission Network
  • Generation and Wholesale Market

On 21 July 2017 and 22 September 2017 respectively, National Grid Interconnectors Limited (“NGIL”) submitted proposed modified Access Rules (the IFA Access Rules) and a proposed modified Charging Methodology (the IFA Charging Methodology) for the IFA interconnector for approval.

We have decided to approve the IFA Access Rules and IFA Charging Methodology proposed by NGIL on the basis that they better achieve the relevant access rules and charging methodology objectives.  This letter contains directions approving the IFA Access Rules and IFA Charging Methodology. It also explains the reasons for our approval as required under section 49A of the Electricity Act 1989.