This letter sets out the Authority’s approval of an increase to National Grid Electricity Transmission’s (NGET’s) Black Start target by £14.9 million.

This approval follows NGET’s formal application for an increase to the Black Start target as part of the mid-scheme update provisions under the balancing services incentive scheme.