This decision sets out our approach to providing a means for interconnector projects of the Third Cap and Floor Window for Electricity Interconnectors that have encountered delays, caused by force majeure events, during the pre-operational period to request a later Regime Start Date for the Authority’s consideration.
You will see our modifications to the standard conditions of the electricity interconnector licence.
We have decided to:
This process largely mirrors the mechanism contained in the new standard condition 26B.
This decision more widely fits within the timelines and incentives framework applied to the Third Cap and Floor Window for Electricity Interconnectors. Separately we published new and modified incentives and concepts for the treatment of interconnector project delivery delays.