Skip to contents

Distribution Charges 

Ofgem has a duty to consider the methodologies used by electricity Distribution Network Operators (DNOs) to set charges for connection to and use of their distribution systems.

DNOs have recently been developing common approaches to charging via the electricity distribution structure of charges project, and:

• from 1 April 2010 DNOs have implemented a common charging approach (the CDCM) at lower voltage levels (HV and LV).
• DNOs are continuing to work towards common charging approaches at the highest (EHV) voltage levels (the EDCM), for implementation from 1 April 2012. These are designed to deliver more forward looking, locational charges.
• from 1 October 2010 DNOs implemented largely common connection charging methodologies.

 

The Distribution Charging and Methodologies Forum (DCMF) is the industry group that discusses charging issues. Proposed changes to CDCM are now progressed through DCUSA under new open governance arrangements, and the new methodology document sits within DCUSA. DNOs maintain separate charging methodologies at EHV, however, when implemented, the EDCM will also sit within DCUSA.

 

Further DNO information on common charging can be found at the following links: EDCM / CDCM. DNOs’ current use of system charges are published in a common spreadsheet format at the following link.

 

Documents on the project to deliver revised charging methodologies are provided via the links below. Other related areas on our website are as follows:


• Modifications to DNOs’ charging methodologies (including modifications to bring in the largely common connection arrangements) are detailed on our ‘Distribution Charging Modifications’ page.
• Links to individual DNO charging documents can be found in the further resources box on the right had side of this page.


DateTitle (Click for more document information)
03/02/2012Collective Licence Modification Direction (amending licence to approve the methodology for Import Charges and delay the approval of the methodology for Export Charges in the EHV Distribution Charging Methodology (EDCM).
02/02/2012Distribution use of system charging – decision and further guidance on higher voltage generation charging
20/12/2011Collective Licence Modification decision (amending the licence obligation to apply a new rule for determining the electricity distribution charging boundary)
20/12/2011Decision on revised timetable for modification to the EHV Distribution Charging Methodology (EDCM) for export charges and deferral of boundary for export customers
20/12/2011Collective Licence Modification Proposal - revised timetable for modification to the EHV Distribution Charging Methodology (EDCM) for export charges and deferral of boundary for export customers
20/12/2011Decision to approve changes to the EHV Distribution Charging Methodology (EDCM) and direction to approve further changes to amend inconsistencies within the EDCM
21/10/2011Use of system charges for distributed generators: publication of consultations on a time-limited exemption for pre-2005 generators and the way forward on higher voltage generation charging
21/10/2011Distribution use of system charging: way forward on higher voltage generation charging
- (Reference number: 134/11)
21/10/2011Distribution use of system charging: a time-limited exemption for pre-2005 generators
- (Reference number: 135/11)
06/09/2011Electricity distribution charging: decision on the methodology for higher voltage import charges
- (Reference number: 116/11)
11/08/2011Decision in relation to a request by CE Electric UK (NEDL) to publish Use of System (UoS) charges that are not in accordance with its charging methodology
11/08/2011Use of system charges for distributed generators (DG) – update on current thinking
02/08/2011Decision to modify the boundary between the Common Distribution Charging Methodology (CDCM) and the EHV Distribution Charging Methodology (EDCM) as set out in the electricity distribution standard licence conditions (SLCs)
02/08/2011Collective Licence Modification Proposal ref. 95/11 (amending the licence obligation to apply a new rule for determining the electricity distribution charging boundary)
- (Reference number: 95/11)
13/07/2011Decision in relation to completion of Common Distribution Charging Methodology (CDCM) approval condition – generation dominated areas
17/06/2011Consultation on request form CE Electric UK (NEDL) to publish use of system (UoS) charges that are not in accordance with its charging methodology.
- (Reference number: 79/11)
13/06/2011Distribution Network Opertators' (DNOs') final report on fulfilling Common Distribution Charging Methodology (CDCM) conditional approval in relation to generation dominated areas
20/05/2011Electricity distribution charging methodologies: distribution network operators’ (DNOs') proposals for the higher voltages
- (Reference number: 67/11)
09/05/2011Charges for pre-2005 distributed generators' use of Distributed Network Operators' (DNOs) distribution systems - proposed guidance
- (Reference number: 58/11)
13/04/2011EHV Distribution Charging Methodology (EDCM) report
01/04/2011Distribution Network Opertators' (DNOs') interim report on fulfilling Common Distribution Charging Methodology (CDCM) conditional approval in relation to generation dominated areas
15/03/2011Consultation letter on a licence change to the boundary between the Common Distribution Charging Methodology and the EHV Distribution Charging Methodology related to Licensed Distribution Network Operators
- (Reference number: 31/11)
07/01/2011Distribution Network Operator (DNO) consultation on common electricity distribution use of system charging methodologies (EDCM) proposals
16/12/2010Collective licence modification direction - Dates for delivering the EHV Distribution Charging Methodology (EDCM) and the new distribution charging boundary rule between higher and lower voltages
14/12/2010Decision in relation to completion of Common Distribution Charging Methodology (CDCM) approval condition – generation dominated areas
17/11/2010Decision on licence modifications in relation to the revised delivery dates for the EHV Distribution Charging Methodology (EDCM) and the new distribution charging boundary between higher and lower voltages
- (Reference number: 141/10)
12/10/2010Distribution Network Opertators' (DNOs') report on fulfilling Common Distribution Charging Methodology (CDCM) conditional approval in relation to generation dominated areas
30/09/2010Derogation regarding revised submission date for the EHV Distribution Charging Methodology (EDCM)
22/09/2010Decision on revised submission and implementation dates for the EHV Distribution Charging Methodology (EDCM)
- (Reference number: 120/10)
27/08/2010Derogation regarding revised submission date for the EHV Distribution Charging Methodology (EDCM)
26/08/2010Electricity distribution charging boundary between higher (EDCM) and lower (CDCM) voltages - Collective Licence Modification Direction
23/08/2010Consultation on revised submission and implementation dates for the EHV Distribution Charging Methodology
- (Reference number: 112/10)
23/08/2010Charges for Pre-2005 Distributed Generators’ use of Distribution Network Operator's (DNO) distribution systems - decision on unbundling
23/07/2010Collective Licence Modification Proposal- Electricity distribution charging boundary between higher (EDCM) and lower (CDCM) voltages
- (Reference number: 92/10)
22/07/2010Electricity distribution charging boundary between higher (EDCM) and lower (CDCM) voltages
- (Reference number: 90/10)
21/07/2010Charges for pre-2005 Distributed Generators’ use of Distribution Network Operators’ (DNOs’) distribution systems
- (Reference number: 88/10)
01/07/2010Electricity distribution charging boundary between higher (EDCM) and lower (CDCM) voltages - Workshop presentation and notes
25/06/2010Electricity distribution charging boundary between higher (EDCM) and lower (CDCM) voltages- Update on illustrative charges
15/06/2010Electricity distribution charging boundary between higher (EDCM) and lower (CDCM) voltages - Impact Assessment
- (Reference number: 72/10)
01/04/2010Revocation of derogation granted to Central Networks pursuant to paragraph 50.36 of Standard Licence Condition 50 of the Electricity Distribution Licence
21/12/2009Derogation requests relieving individual DNOs of the requirement to comply with certain elements of the common charging methodology at lower voltages from April 2010
21/12/2009Electricity distribution structure of charges project: Decision on Distribution Network Operators(DNOs) submission to meet the conditions for approval of the CDCM required by 31 December 2009
- (Reference number: 163/09)
20/11/2009Electricity distribution structure of charges: the common distribution charging methodology at lower voltages
- (Reference number: 140/09)
09/11/2009Authority approval of EDF Energy (IDNO) Ltd's Use of System Charging Methodology
28/09/2009Open letter: Update on impact of common distribution charging methodology and DPCR5 on distribution customer charges from 1 April 2010
28/09/2009Electricity distribution structure of charges project: Distribution Network Operators' proposals for a common methodology at lower voltages
- (Reference number: 114/09)
25/09/2009Common Distribution Charging Methodology (CDCM) Report
04/08/2009Open letter: Impact of common distribution charging methodology and DPCR5 on distribution customer charges from 1 April 2010
31/07/2009Delivering the electricity distribution structure of charges project: decision on extra high voltage charging and governance arrangements
- (Reference number: 90/09)
02/07/2009Consultation on common electricity distribution use of system charging methodology
08/05/2009Collective Licence Modification intended to deliver the electricity distribution structure of charges project at lower voltages
20/03/2009Next steps in delivering the electricity distribution structure of charges project: decision document
- (Reference number: 24/09)
18/12/2008Decision on IDNO and DNO out of area use of system charges: reduction of the 3 month notice period for amending charges under SLC 14.20
- (Reference number: 169/08)
11/12/2008Next steps in delivering the electricity distribution structure of charges project - consultation
- (Reference number: 160/08)
03/11/2008Consultation on IDNO and DNO out of area use of system charges: reduction of the 3 month notice period for amending charges under SLC 14(20)
- (Reference number: 149/08)
01/10/2008Delivering the electricity distribution structure of charges project
- (Reference number: 135/08)
22/07/2008Delivering the electricity distribution structure of charges project: decision on a common methodology for use of system charges from April 2010, consultation on the methodology to be applied across DNOs and consultation on governance arrangements
- (Reference number: 104/08)
06/05/2008Authority approval of IPNLs use of system charging methodology
06/05/2008Authority approval of ENCs use of system charging methodology
02/04/2008Delivering the electricity distribution structure of charges project
- (Reference number: 36/08)
25/01/2008Authority approval of Laing O'Rourke's use of system charging methodology
25/01/2008Authority approval of Laing O'Rourke's connection charging methodology
04/05/2007Implementation steering group meeting minutes 13 March 2007
03/04/200778/07 - Structure of electricity distribution charges: update on progress and next steps
- (Reference number: 78/07 )
22/01/2007Implementation Steering Group meeting minutes 30 January 2007
22/11/2006Implementation Steering Group meeting minutes 28 November 2006
19/10/2006CE Electric charging methodology condition - Authority decision letters
10/10/2006Implementation Steering Group meeting minutes 17 October 2006
30/08/2006Implementation steering group meeting minutes 5 September 2006
11/07/2006Implementation Steering Group meeting minutes 18 July 2006
21/04/2006Distribution losses percentages by DNO area 1998/99 to 2003/04
19/04/2006Implementation Steering Group meeting minutes 25 April 2006
01/03/2006Implementation Steering Group meeting minutes 7 March 2006
17/01/2006Implementation Steering Group meeting minutes 24 January 2006
13/01/2006Electricity distribution use of system charging: Bath University benefits analysis report on the long term charging framework
- (Reference number: 12/06)
15/12/2005Implementation Steering Group meeting minutes 13 December 2005
24/11/2005Implentation Steering Group meeting minutes 8 November 2005
15/11/2005DNO charging methodology conditions - Authority decision letters
19/10/20052006-07 electricity distribution use of system EHV charges
- (Reference number: 227/05)
07/10/2005Implementation Steering Group meeting minutes 27 September 2005
26/07/2005Implementation Steering Group meeting minutes 5 July 2005
06/06/2005May 2005 workshop - longer term charging framework
01/06/2005Implementation Steering Group meeting minutes 12 April 2005
09/05/2005Structure of electricity distribution charges - Consultation on the longer term charging framework
- (Reference number: 135/05)
25/04/2005DNO charging methodology conditions - Authority decision letters
25/04/2005EDF: DNO charging methodology conditions - Authority decision letter
25/04/2005SP Distribution: DNO charging methodology conditions - Authority decision letter
25/04/2005SP Manweb: DNO charging methodology conditions - Authority decision letter
25/04/2005United Utilities: DNO charging methodology conditions - Authority decision letter
24/03/2005Electricity Distribution: Academic reports on the long term charging framework
16/03/2005Structure of charges: Implementation Steering Group meeting - 1 March 2005
11/02/2005EHV Demand Transition letter
- (Reference number: 35/05)
11/02/2005Authority Approval of WPD methodologies
- (Reference number: 36/05)
11/02/2005Authority Approval of United Utilities methodologies
- (Reference number: 37/05)
11/02/2005Authority Approval of Scottish-Southern methodologies
- (Reference number: 38/05)
11/02/2005Authority Approval of Scottish Power methodologies
- (Reference number: 39/05)
11/02/2005Authority Approval of EDF Energy methodologies
- (Reference number: 40/05)
11/02/2005Authority Approval of DNO Charging Methodologies
- (Reference number: 43/05)
11/02/2005Authority Approval of Central Networks methodologies
- (Reference number: 41/05)
11/02/2005Authority Approval of CE Electric methodologies
- (Reference number: 42/05)
02/02/2005Implementation Steering Group meeting minutes 18 January 2005
07/01/2005Implementation Steering Group Terms of Reference
17/12/2004Transition of Electricity Distribution EHV demand use of system charges
- (Reference number: 284/04)
13/10/2004Structure of electricity distribution charges - Proposed DNO charging methodology statements
- (Reference number: 235/04)
30/07/2004Structure of Electricity Distribution Charges: Open letter consultation on DNO draft charging methodologies for demand customers and generators
- (Reference number: 183/04)
08/07/2004Structure of Electricity Distribution Charges Implementation Steering Group (ISG) - Notes from 22 June 2004 meeting
26/04/2004Minutes from Structure of Electricity Distribution Charges Implementation Steering Group (ISG) 18 March 2004
06/04/2004Structure of distribution charges; update and licence modifications
- (Reference number: 76/04)
24/02/2004Notes from the Structure of Electricity Distribution Charges Implementation Steering Group (ISG) Jan 29 2004
24/02/2004Structure of Charges - Interim Arrangements Use of System Charges
01/12/2003Electricity distribution rebates to suppliers
- (Reference number: 155/03)
14/11/2003Structure of Electricity Distribution Charges - Initial decision
- (Reference number: 142/03)
10/10/2003Implementation Steering Group Proposed - Terms of Reference
21/08/2003Notes from Structure of Charges workshops - July 2003
30/07/2003Electricity distribution rebates to suppliers - A consultation document
- (Reference number: 74/03)
30/06/2003Structure of charges working group meeting - 5
12/06/2003Structure of Electricity Distribution Charges: Initial conclusions
- (Reference number: 43/03)
12/06/2003Electricity Distribution Losses: Initial Proposals
- (Reference number: 44/03)
14/04/2003Electricity Distribution Losses Workshop 14 April 2003 Programme
25/03/2003Structure of Charges Working Group Meeting 4
05/03/2003'Distribution Charges Feb 2003 Workshop - Welcome'
18/02/2003Structure of charges working group meeting notes - meeting 3
28/01/2003Fault levels and distribution charges - a note from ILEX to the ISG
15/01/2003Electricity distribution losses - A consultation document
- (Reference number: 03/03)
09/12/2002Structure of charges working group meeting notes - meeting 2
24/10/2002Structure of Electricity Distribution Charges. Update Document
- (Reference number: 69/02)
21/12/2000The Structure of Electricity Distribution Charges 2000
- (Reference number: 00/00)