ScottishPower - Capacity Market Rules CP210

Change Proposal

Publication date

This proposal seeks to amend Rules 13.4.1 and extend the duration of one of the required Satisfactory Performance Days to a length of four consecutive half-hourly settlement periods. It is suggested this requirement come into effect from the 2017/18 Delivery Year for agreements won following 1 December 2016. It is proposed the new testing requirements do not apply for the Transitional Arrangements.

Change proposal status

Closed (rejected)

Proposal rules area

Testing Regime

Proposal organisation

Scottish Power