Settlement reform highlights

    Business Case and Impact Assessment: Strategic Outline Case published on 8 February, using HM Treasury Best Practice Five Case Model guidance.

    Target Operating Model (TOM):  In accordance with stage 1 of the TOM design, the ELEXON led Design Working Group have developed five high level skeleton TOMs. These TOM options will now be evaluated by both the Design Working Group and the Design Advisory Board before being provided to the Ofgem SRO.   Elexon held a well-received workshop on 28 February to explain the TOM work so far to stakeholders.

    HHS Stakeholder Telephone Conference: Latest teleconference held on Thursday 22nd February. Thank you to all stakeholders who attended.

    We welcome feedback on our stakeholder teleconferences and stakeholder engagement work. We would appreciate it if you could complete this survey, by 31st March. It shouldn’t take longer than 5 minutes to complete. Some of the survey data will be shared with Elexon.

    Our next teleconference is planned for Thursday 12 April at 13.00 – 14.00.

      Your feedback and future updates

      To subscribe to receive this update in future, subscribe to the Ofgem Daily Update and select 'Electricity - retail markets' in the preference centre.  

      If you have any feedback or enquiries, please contact us at half-hourlysettlement@ofgem.gov.uk.