Determination on SHE Transmission’s proposal for reducing visual amenity impacts in the Loch Tummel National Scenic Area

Decision

Publication date

Company

Industry sector

Transmission Network

Licence type

Electricity Transmission Licence

As part of the RIIO1 price control, Ofgem introduced a new policy for electricity transmission owners (TOs) to reduce the visual impact of pre-existing infrastructure in nationally designated areas. The expenditure cap for all mitigation projects that come forward under the scheme during the RIIO-T1 price control is £500 million (2009/10 prices) in total.

This letter explains our determination on SHE Transmission’s proposal for reducing visual amenity impacts in the Loch Tummel National Scenic Area under RIIO-T1 provisions for the mitigation of pre-existing infrastructure.

Alongside this letter, we’re publishing a notice under Part C of Special Condition 6G of the Electricity Transmission Licence on modifications to SHE Transmission’s electricity transmission licence and allowed revenue to implement our decision. Details of the changes are set out in the notice.

Please respond on or before 15 November 2019 to Dale.Winch@ofgem.gov.uk