Determination on new outputs in National Grid’s electricity transmission price control

Decision

Publication date

Company

Industry sector

Transmission Network

Licence type

Electricity Transmission Licence

This letter explains our determination on new Enhancing Pre-existing Infrastructure (EPI) outputs and a related adjustment to National Grid Electricity Transmission’s (National Grid) allowed expenditure under the RIIO ET1 price control.

Alongside this letter, we’re publishing a notice under Part C of Special Condition 6G of the Electricity Transmission Licence on modifications to National Grid’s electricity transmission licence to implement our determination. Details of the changes are set out in the notice.

Please respond on or before 26 July 2019.