Decision to make licence modifications for the proposed Kintyre Hunterston reinforcement under the Strategic Wider Works (SWW) arrangements

Licence modification

We are publishing our decision under section 11A(1)(a) of the Electricity Act 1989 to make modifications to Scottish Hydro Electric Transmission plc’s (SHE Transmission’s) electricity transmission licence.  This follows a statutory consultation on the proposed licence changes which we published on 18 December 2013 (the December consultation).  The modifications will take effect on 16 September 2014.

This document includes:

  • The proposed modification in our consultation
  • The responses to our December consultation
  • Amendments to proposed licence modifications since December

We are also publishing the Decision Notice, which details the modifications to SHE Transmissions Electricity Transmission Licence including any minor alterations we have made since the statutory consultation.

Subsidiary documents