Decision further to Limejump Energy Limited’s request for Derogation under Standard Condition 11.1 (Compliance with Grid) of the Electricity Supply Standard Licence Conditions
Decision
Limejump Energy Limited has submitted a derogation request from the obligation for the data required in clauses BC1.4, BC1.A.1.3.1, BC1.A.1.3.2 and BC1.A.1.5 to be submitted at a Grid Supply Point (GSP) level.
This letter sets out our decision to grant the requested derogation. The Direction published alongside this decision letter gives effect to this decision.