Consultation on additional Transmission Investment Incentives 2012-13 funding for National Grid Electricity Transmission plc

Consultation
  • Upcoming
  • Open
  • Closed (awaiting decision)
  • Closed (with decision)

Publication date

Closing date

Company

Industry sector

Transmission Network

Decision

This consultation seeks views on whether to approve additional funding for National Grid’s Anglo-Scottish Incremental project, which will increase capacity across the transmission boundary between Scotland and England. National Grid is seeking retrospective (2012-13) Transmission Investment Incentives (TII) funding of £8.4 million for construction work at the Hutton substation.

We have reviewed National Grid’s request and are minded to approve it under the Further Works mechanism set out in National Grid’s electricity transmission licence. Our decision is subject to consideration of the responses to this consultation.

 

We invite responses to this consultation by 30 May 2014.